2020 Street Project

Project Updates

Below are the most recent project updates and their informational documents. If you have questions, please contact the Engineering Division at 763-572-3554.

July 30, 2020

A temporary watermain connection will be provided to homes while watermain replacement occurs over the next week on Ely, Liberty and Longfellow Street. Detailed information can be found in the emailed public notice. Please contact Engineering with questions.

Official Emailed Notice - July 30th, 2020 (PDF)

July 20, 2020

Construction is anticipated to being the week of July 27th and will begin with pavement removal and replacement, concrete curb, watermain and fire hydrant replacement. More information can be found, including a tentative construction schedule, in the latest emailed public notice found at the link below. 

Official Mailed Public Notice (PDF) July 20, 2020

July 2, 2020

The City has awarded the project to C&L Excavating of St. Joseph, MN. A preconstruction meeting will be held on Wednesday, July 8th and we will have a more formalized project schedule to share. It is anticipated construction will begin in late July. More information can be found in the emailed update to residents found below. Please sign up for updates by emailing web-StreetProjects@fridleymn.gov.

Official Mailed Notice (PDF)

May 5, 2020

Information was mailed to affected residents on Tuesday, May 5th regarding the tentative construction schedule and information on how to get updates during the project due to the pandemic. All information will be posted on the project website as well as via email. You can sign up for email updates by contacting web-streetProjects@fridleymn.gov

Official Mailed Notice

April 22, 2020


The City of Fridley’s 2020 Street Rehabilitation Project is anticipated to begin this summer. The project is currently out for bids. A start date will be available once a contractor is awarded the project mid-May. Given the current pandemic the City will be posting future project updates and notifications on the 2020 Street Project page. Residents are encouraged to contact web-StreetProjects@fridleymn.gov and request to be added to the mailing list to receive project updates via email.

November 25, 2019

A public hearing was held on Monday, November 25 at 7 p.m.

A preliminary assessment notice was mailed to all affected properties. A copy of the questionnaire will also be mailed out to all properties. We are also seeking feedback for this project on Polco.

Open House Presentation

An open house was held on Wednesday, September 17th to give an overview of the project and what to expect. If you were unable to attend this open house or would like to review the presentation, you can download the presentation. 

September 17th Presentation

You can also fill out the Street Project Questionnaire at online.This information is important for the project managers as they design and plan for the project. Below is the assessment map. 

If you have further questions please contact Engineering at 763-572-3554.

Subscribe to Email or Text Notifications

To subscribe to email or text notifications, visit our Fridley 4U notifications page and enter your email. Select whether you would like to receive your notifications by text, email or both. 

Below will be list of various topics you can subscribe to, including 2020 Rehabilitation Project.

Note: Please remember to set your spam blocker to allow mail from listserv@civicplus.com.

Project Overview

The project area is bounded by Ashton Avenue to the east, East River Road to the west, Ironton Street to the north and 79th Way to the south. The work will include pavement resurfacing, concrete curb repairs, watermain replacement in select segments, aging fire hydrant replacement and miscellaneous utility maintenance. The proposed improvements will be presented at the open house tentatively scheduled for 6:00 PM, September 17th, at City Hall.

FAQs

A list of frequently asked questions (FAQs) and construction information can be found here. Please contact Engineering if you have further questions at 763-572-3554.

Assessment Map 200422 Opens in new window

ST2020-01 Street Rehabilitation Project Map 190806